Assignment 1
Project Management
Description | Marks out of | Wtg (%) | Due date |
Assignment 1 Project Management | 200 | 20.00 | 17 Aug 2015 |
Objectives
This assignment addresses the following objectives for the course as outlined in the course specification:
- Define and describe engineering project management
- Utilise CPA management techniques to plan, analyse, schedule and control engineering and surveying projects
Special Instructions
This assignment is to be electronically submitted via Study desk assignment drop-box.
Please submit as a generated PDF file or Word file. Do not submit zip files or scanned PDF files.
File name for your assignment may follow the following format:- Student surname (in capitals)_first name_ENG4004_ASS 1_S2_2015
For example JONES_Bob_ENG4004_ASS 1_S2_2015
This is not critical but helps in sorting student submissions.
QUESTION 1 (20 marks)
A project involves fourteen (14) activities identified by the code letters A to N. The table below indicates the sequence in which the activities must be undertaken. Construct an “Activity on Arrow” network diagram, for the project.
Activity | Code letter of any immediately preceding activity or activities |
A
B C D E F G H I J K L M N |
–
– B A A, B A C, E C F F, G, H I K, J J J |
QUESTION 2 (100 marks)
The network for a project is shown below. Activity times, in days, are indicated by the figure that appears under each activity.
- Analyse the network to determine the earliest and latest event times and the minimum project duration. Indicate the critical path for the project. (25 marks)
- What amount of free float is associated with activity 2-6? (5 marks)
- Neatly sketch a sequenced bar chart, not a Gantt chart, for the above project with all activities shown at their earliest start times. (25 marks)
The number of people required for each activity is shown in the following table. The duration of individual activities cannot be altered by the allocation of additional people, nor may activities be divided into smaller components performed at different times.
- Indicate the number of people required on each day of the project with all activities at their earliest start times. (5 marks)
- By utilizing the floats in the various activities, smooth the daily requirement for people as much as possible. What is the minimum ceiling of people required to complete the project in minimum time? Justify your answer by redrawing the bar chart and indicating the people required on each day. (40 marks)
Activity | People Required Per Day | |
1-2
1-3 1-4 1-6 |
6
4 7 3 |
|
2-6
3-5 3-7 4-5 |
2
1 1 5 |
|
4-8
5-9 6-9 7-9 8-9 |
6
4 3 2 3 |
QUESTION 3 (70 marks)
For the network shown below, the normal and crash durations for the activities in the project, and their associated costs, are shown in the table following. Indicate what activity or activities should be crashed to reduce the project time by:
(i) 2 days, and
(ii) 4 days
Estimate the increased costs that are incurred in each case.
Activity | Normal Duration | Crashed Duration | ||
Days | Cost
($) |
Days | Cost
($) |
|
1-2
1-3 2-3 2-4 2-5 |
4
2 12 7 13 |
200
250 1200 1200 1500 |
3
2 10 6 10 |
230
250 1400 1300 1800 |
3-7
4-6 5-6 5-7 6-7 |
15
5 5 4 11 |
100
250 150 150 75 |
10
3 5 3 6 |
200
310 150 175 175 |
QUESTION 4 (10 marks)
The following information has been computed from a project:
Expected total project time = 62 weeks
Project standard deviation = 10
What is the probability that the project will be completed 18 weeks before its expected completion time?
===========ABOUT ASSIGNMENT TASK ===========
AssignmentTask.com provides high-quality assignments help at wide range from Australia – UK & USA academic experts and also guarantees to make sure delivery assignments on time @ reasonable rate. OUR ASSIGNMENT EXPERT WRITERS MAKES EFFORTS TO DELIVER BEST QUALITY ASSIGNMENT HELP, ESSAY HELP, CASE STUDY HELP AND DISSERTATION EDITING HELP on each Order. 100% satisfaction is our primary motto. Our customers get 24 x 7 hours live chat supports.